|
Baling the Vault
vault project main page
Morning in the desert before the vault
raising. The vertical walls and the bond beam on top of them
were in place. Plywood falsework was erected. Bales, water and
food are on hand.
Horizontal rebar spreads the load from tie wires along the mesh.
The inside bar was notched into place on the falsework, and the
mesh was wrapped over....
Creating a big birdcage. The 2" x 2" wire mesh was
tied to the rebar.
The same rebar/mesh layer would later be placed on the outside
of the vaults, and the tension wires would be inserted between
bale courses and tied inside and out (see diagram)
Boards were stretched across the buttress and bedroom walls to
provide staging for placing the bales. Most of the first day
was spent running mesh and clamping the first course of bales
to the bond beam.
Pulley cranes were erected on each side of the vault, bales were
hooked and pulled up onto the staging level, then set into place.
Raising the bales was one of the most popular jobs.
Owner Lou Harrison and some of the crew of volunteers.
Janet Johnston, project architect and Sabina, Dog-on-Site, take
a short break once the baling crews had learned their jobs and
hit their stride.
Work on the second day progressed rapidly.
Janet and George set one of the last bales.
By sundown the second day, the vault was complete.
Lou in the (shady) bale tying headquarters.
more
|
|